Engineering (Overview)

Engineering (Overview)

Engineering is the module where Bills of Materials, Routings, and Operation Definitions all live together, along with the Engineering Changes that keep them under control. It's the central place where product structure, production sequencing, and shared operation standards are defined and maintained.

Overview

  • Engineering brings BOMs, Routings, and Operation Definitions together in one place.

  • Operation Definitions act as a shared library — Routings pull their defaults from them instead of repeating setup/run times on every operation.

  • Engineering Changes track and control updates to BOMs and Routings: they show what a change reaches, go through approval, and then carry the change into the affected BOMs and open work orders instead of leaving them to be edited one by one.

Where to Access

  • Users can access Engineering via Manufacturing column (Manufacturing: Engineering)

Key Attributes

Bills of Materials
FieldDescription
Item / RevisionBOMs are listed by item and revision; select a revision to open that BOM
Item (component line)The specific part or material needed
DescriptionA short note on the component (optional)
QuantityAmount needed to build one unit
UOMUnit of measure
Unit Cost / Total CostCost per unit, and Quantity × Unit Cost
Issue atThe operation number the component is issued at, if needed partway through the routing rather than at the start
Routings
FieldDescription
ItemSelect an item to open its routing
Fill from definitionPulls setup and run times straight from the operation's shared Operation Definition instead of entering them manually
ResourcesShows the labor, machines, or tools that specific operation requires
Operation Definitions
FieldDescription
CodeShort identifier for the operation
Operation Typee.g. Manufacturing
ActiveWhether the definition is currently usable
DescriptionWhat the operation does
Default Work CenterApplied automatically whenever this definition is selected on a routing operation
Effective From / Effective ToDate range the definition is valid for

Standards — default values every operation using this definition starts with (leave a field blank and the operation keeps its own value):

FieldDescription
Setup TimeDefault setup time
Runtime / UnitDefault runtime per unit
Overlap QuantityUnits to send ahead to the next operation before the full batch finishes
Completion BehaviorHow the operation is marked complete
Reporting BasisWhat one Start/Complete report actually counts as
Default Work InstructionLinked work instruction document
RecordableWhether the operation's execution is logged
Count pointWhether this operation is a count point in the routing

Resources — simultaneous resource requirements copied to every released Work Order and scheduled together:

FieldDescription
RoleLabor, Primary Machine, Tool, or Auxiliary
Target typeResource or Resource Pool
TargetThe specific resource or pool selected
UnitsQuantity of the resource required
Setup minSetup time for this resource, in minutes
Run min / unitRun time per unit for this resource, in minutes
BasisItem or Batch
PostingAutomatic or Manual
Engineering Changes
FieldDescription
TitleWhat's changing, in one line (required)
ReasonCustomer request, Design error, Supplier, Regulatory, or Internal
SourceManual, Project change order, or CAD import
Effective DateLeave blank to take effect as soon as the change is applied
ProjectOptional — link the change to a project
Change orderOptional — pick one of the selected project's change orders
Change linesEach line names a part and a Change Type — Add, Remove, Replace, Quantity, Revision, or Routing. A line with no specific BOM applies to the current version of every BOM that uses the part

An Engineering Change moves through Draft → Pending Approval → Approved → Applied. Preview impact lists the BOMs, work orders and other records the change reaches before you submit; after approval, Apply change creates the new BOM revisions and updates open work orders. See Engineering Changes (ECO) for the full process.

See It in Action: A Tour of Engineering

Watch a walkthrough of the Engineering module — Bills of Materials, Routings, Operation Definitions, and Engineering Changes — all in context.

Key Functions

FunctionHow to do it
Build a BOMManufacturing → Engineering → BOM → select a revision to view or edit its component lines
Define a RoutingOpen an item's routing, add operations, and use Fill from definition to pull standard setup/run times instead of retyping them
Maintain Operation DefinitionsKeep a shared library of operations (code, standards, resource requirements) so every routing that uses them stays consistent
Submit an Engineering ChangeManufacturing → Engineering → Changes → Add New (or Start Engineering Change from a BOM row) → set Title, Reason and Effective Date, add change lines, press Preview impact, then Submit. Once approved, press Apply change to carry it into the BOMs and open work orders it affects

Maintain accuracy (recommended practice):

PracticeWhy
Keep Operation Definitions currentSo Routings that pull from them stay accurate
Route BOM/Routing edits through Engineering ChangesPreserves an audit trail instead of editing live records directly
Review Resource requirements on Operation DefinitionsKeep them current when equipment or staffing changes